Croatian National Plan for Broadband Development 2021–2027 responds to the European Gigabit Society objectives 2025 and partially to the 2030 digital targets.
Summary of broadband development in Croatia
The National Plan for Broadband Development 2021-2027 aims at providing the download speeds of at least 100 Mbps to all households with the possibility to upgrade to 1 Gbps, and 1 Gbps for government offices and public buildings such as schools and health facilities. The 5G networks are to cover all main cities and towns and major highways.
National broadband strategy and policy
Responsible authorities
- The Ministry of the Sea, Transport and Infrastructure (Ministarstvo mora, prometa i infrastrukture) is the central state administrative body with expertise and responsibility for administrative tasks in the area of electronic communications including broadband policy and strategy. Through the Directorate for air traffic, electronic communications and postal services, it is in charge of preparing proposals for strategies, studies, guidelines, programmes and implementation plans. It establishes the general principles and objectives of the policy for the development of electronic communications networks and services, including broadband infrastructure.
- The Ministry of Regional Development and EU Funds (Ministarstvo regionalnoga razvoja i fondova Europske unije) is managing two national EU-funded NGN schemes, the Framework National Programme for the Development of Broadband Access Infrastructure and the National Programme for Backhaul Broadband Infrastructure Development.
- The Croatian Regulatory Authority for Network Industries HAKOM (Hrvatska regulatorna agencija za mrežne djelatnosti) ensures market competition, stable growth and environment for innovations in the electronic communications and postal services market.
Main aims for broadband development
The government of the Republic of Croatia adopted the National Plan for Broadband Development 2021-2027 in March 2021. The plan responds to the European Gigabit Society objectives 2025, partially the 2030 digital targets and the 5G for Europe Action Plan. The Croatian plan aims to provide connectivity with download speeds of at least 100 Mbps to all households, while providing government offices and public buildings such as schools and health facilities with symmetric connections of at least 1 Gbps. It also seeks 5G networks in all main cities and towns and along major highways.
The Digital Croatia Strategy until 2032, a multi-sectoral strategic planning act, was approved in 2022 and sets the following main strategic objectives:
- developed and innovative digital economy
- digitalised public administration
- developed, available and taken-up Very High Capacity Networks
- developed digital competences for working and living in a digital age
Main measures and financial instruments for broadband development
For broadband mapping, HAKOM has developed and updates a central mapping tool, called Interactive GIS portal, which provides information about the availability of broadband access, a consolidated plan of mobile communications infrastructure as well as publications of intents for deployment and bandwidth speeds.
The National Framework Programme for the Development of Broadband Backhaul Infrastructure in Areas Lacking Sufficient Commercial Interest for Investments (ONP) is a national (umbrella) broadband state aid scheme. Besides general state aid rules, ONP also brings guidelines for local municipalities for implementation of individual projects within ONP. The total estimated (maximum) funding at the national level for the framework programme amounts to EUR 257.9 million, of which EUR 123.1 million is to be financed from ERDF and the remaining EUR 134.8 million to be covered by the EIB loan. Both sources of funding (ERDF and EIB loan) represent grants for public authorities at local and regional level (cities, municipalities and counties). It is expected that the contribution of private funds in co-financing NGA broadband networks during the implementation of the Programme will amount to EUR 120 million. The average annual budget of the Programme in 2016 - 2023 amounts to EUR 31.5 million. The Croatian Regulatory Authority for Network Industries (HAKOM) has been determined as a holder of the ONP.
The national programme for broadband backhaul infrastructure (NP-BBI) covers state aid measures for backhaul portion of NGN network in white areas and aims at developing the national NGN broadband backhaul, as a network segment interconnecting NGA networks and national core networks. The Programme was endorsed by the European Commission and will be carried out through a public investment model. The passive fibre infrastructure will be designed and built and retained in permanent public ownership. After the infrastructure is built, it will be offered to operators on the market at equal terms. Based on the results of public consultations, the Programme aims to cover at least 540 settlements, which are initially prioritised and set as targeted settlements (at least 25% of population), located in suburban and rural areas of Croatia. The overall estimated (maximum) budget of the measure is EUR 101.4 million, of which EUR 86.2 million (85%) will be funded by ERDF and the remaining EUR 15.2 million (15%) by national funds. The annual budget of the scheme amounts to EUR 14.5 million for the period 2017-2023.
Within the new Partnership agreement and new Operational programme “Competitiveness and Cohesion”, two activities are proposed for the period 2021-2027:
- Next generation broadband infrastructure scheme: the construction of a next generation broadband ‘backhaul’ infrastructure, along with connections to end-users, which will support access speeds of 100 Megabits per second (Mbps). The scheme covers 540 priority settlements which each have more than 1.000 inhabitants, plus around 5.800 smaller settlements. All the places covered by the investment are demographically, socially and economically below the national average. Around 5.650 km of fibre will be installed. Where possible, existing ducts will be used, though it is estimated that new ducts will be required for approximately 45% (about 2.450 km) of the deployed fibre. The scheme is split into two units: one covers construction of the next generation network backhaul infrastructure; the other covers connection of public administrations to the fibre infrastructure. Total investment for the scheme is EUR 129,1 million, with the EU’s European Regional Development Fund contributing EUR 86,2 million through the “Competitiveness and Cohesion” Operational Programme for the 2014-2020 programming period. The investment falls under the priority “Use of Information and Communication Technologies”. Croatia contributes EUR 42,5 million.
- Investments in the deployment of very high capacity networks in NGA white and grey NGA areas to end users in accordance with the Program for support of the Digital Connectivity, with Croatia’s contribution of EUR 57,5 million.
The Croatian Recovery and Resilience Plan includes connectivity measures to strengthen connectivity as a cornerstone of the digital transition of society and the economy. Worth around EUR 106 million, they aim to provide VHCN connectivity services in line with the EU Gigabit Society objectives 2025:
- 100 Mbps services to 100,000 Croatian households (700,000 inhabitants) in 20 projects in as many local government units, to overcome in particular the connectivity barrier to teleworking and distance learning, especially in rural areas and among vulnerable groups such as students from disadvantaged families or those with disabilities
- 1 Gbit services to all major socio-economic drivers such as schools, universities, research centres, transport hubs, hospitals, public administrative authorities and businesses.
Other RRF investments of about EUR 20 million will target: (i) building passive electronic communications infrastructure to provide access to VHCN and 5G services in rural and sparsely populated areas where there are no the market conditions to attract private investment’; and (ii) 5G coverage in urban areas and the main terrestrial transport routes (5G corridors). About 55% of the households covered by these measures are in rural areas, 26% are in suburban areas, and only 19% in urban areas. About EUR 400,000 will be invested in reform activities on reduction of barriers and guidelines for construction and permit granting as well as harmonisation procedures.
In its roadmap to implement the Connectivity Toolbox, Croatia announced plans to address the main obstacles to efficient VHCN deployment, such as planning restrictions, faster procedures to rights of way, and the need to establish a coordination body for permit handling and draw up guidelines for application of fees.
Data on broadband development and technologies in Croatia
For the latest data on broadband coverage, subscriptions and penetrations, coverage of different broadband technologies check the country reports of the Digital Economy & Society Index (DESI).
Spectrum assignments for wireless broadband
For details on harmonised spectrum assignments, please consult the European 5G Observatory report.
National and EU publications and press documents
English
- Investment scheme: Construction of National Next Generation Network Broadband Backhaul Infrastructure and Connecting the Targeted End-users within a Group of Public Administration Bodies to the Next Generation Access Broadband Infrastructure
- Broadband Investment Handbook
- Mobile and Fixed Broadband Prices in Europe 2022
- Study on National Broadband Plans in the EU27
- Broadband Connectivity Reports and Analyses
Croatian
- Nacionalni plan razvoja širokopojasnog pristupa u Republici Hrvatskoj u razdoblju od 2021. do 2027. godine
- Okvirni nacionalni program za razvoj infrastrukture širokopojasnog pristupa (ONP)
Contact information
BCO Croatia (national Broadband Competence Office): Croatian Regulatory Authority for Network Industries, Development Programmes Department (HAKOM, Hrvatska regulatorna agencija za mrežne djelatnosti)
Address: Roberta Frangeša Mihanovića 9, 10110 Zagreb, Croatia
Contact via email
Phone: +385 1 700 7399
Website
Ministry of the Sea, Transport and Infrastructure (Ministarstvo mora, prometa i infrastrukture)
Address: Prisavlje 14, 10000 Zagreb, Croatia
Contact via email1 or email2
Phone: +385 1 6169 -060 / -110
Website
Latest News
Related Content
Big Picture
Find current information on broadband development in each country, as well as national strategies and policies for developing broadband.
See Also
Sweden’s national broadband plan, adopted in 2016, has the vision of an entirely connected Sweden and has goals for both mobile coverage and for high-speed broadband connections for households and businesses.
Digital connectivity and 5G rollout are among the ten strategic priorities of the Spain Digital Agenda.
Slovenia opts for technological neutrality and market dynamics in developing broadband networks, in particular infrastructure- and service-based competition.
Slovakia has set the long-term objective of providing all households with access to ultra-fast internet by 2030.
Romania focuses on building up a national broadband network as a step towards achieving the EU connectivity targets.
The Agenda Portugal Digital and the National Strategy for Connectivity in Very High Capacity Electronic Communication Networks for 2023-2030 shape development of digital infrastructure in Portugal.
Poland’s national broadband plan 2025 is in line with the EU’s Gigabit Society targets.
Expanding reliable and strong digital infrastructure and closing the digital divide is in focus of the digital infrastructure policies in the Netherlands.
Malta’s broadband policy is technology-neutral and favours a competitive market environment.
The development of a communication infrastructure with a target of gigabit broadband access throughout the country is one of the priorities in the governmental programme of Luxembourg.
Lithuania aims to provide 100 Mbps by 2027 to rural areas as well supporting the Gigabit society targets 2025.
Latvia supports the Gigabit society targets and aims at 100 Mbps, upgradable to gigabit, for urban and rural areas and 5G coverage for all large urban areas.
The Italian Strategy for Ultra Broadband aims to provide gigabit connectivity to all by 2026.
The national broadband plan for Ireland foresees that by 2026 all premises in Ireland will have access to high-speed broadband.
Hungary’s National Digitalisation Strategy 2022-2030 aims to achieve a target of 95% of households covered by gigabit networks by 2030.
The National Broadband Plan 2021-2027 promotes the use of fixed very high capacity and 5G networks. The Greek Digital Transformation Bible 2020-2025 highlights connectivity as one of the five strategic axes and acknowledges the Gigabit Society 2025 targets.
The 2021 coalition agreement, the Digital Strategy and the Gigabit Strategy 2022 of the German Federal Government prioritise the nationwide supply of FTTH and 5G networks.
The Finnish authorities favour a competition-driven, fibre-based network roll-out assisted by public funds for underserved areas and advice for local municipalities on how to deploy broadband networks.
Estonia has established basic broadband coverage throughout the country. The Estonian Digital Agenda sets ambitious targets for 2030.
A number of political initiatives aiming at nation-wide fixed and mobile broadband coverage support Danish broadband goals. The Government works towards making Denmark a digital frontrunner by creating a foundation for Danish businesses to exploit digital technologies.
The National Plan for the Development of Very High Capacity Networks, approved in March 2021, defines the strategic approach of the Czech Republic to the construction of VHCN.
Cyprus’ broadband plan sets strategic objectives for 2021-2025 and includes legislative and regulatory interventions as well as practical support for the development of broadband infrastructure.
The National Broadband Infrastructure Plan for Next Generation Access "Connected Bulgaria" and the Policy on electronic communications were updated and adopted in August 2020.
Belgium’s broadband strategy is incorporated into a broader policy strategy, called Digital Belgium. The aim of the national plan for fixed and mobile broadband is to eliminate the remaining white areas where high speed services are unavailable. By lowering costs and reducing...
Austria’s broadband strategy focuses on the nationwide supply of Gigabit connections (fixed and mobile) by 2030.